Here is the current projected timeline for the project:
| Project Announcement |
August 9, 2006 |
| Air Permit Filing with Arkansas Dept. of Environmental Quality (ADEQ) |
August 9, 2006 |
| Land Acquisition |
October 2006 |
| Regulatory Filings AR, LA, TX |
November 2006 |
| Major EPC Contract |
May 2007 |
| AR CECPN |
4th Quarter 2007 |
| LPSC Approval |
March 2008 |
| Texas CCN |
Anticipate 2nd quarter 2008 |
| Permit to Install from ADEQ |
Summer 2008 |
| Mobilize Site Pre-construction Preparation |
1st Quarter 2008 |
| Energize Auxiliary Transformers |
Revised, TBD after construction begins |
| Boiler First Fire |
Revised, TBD after construction begins |
| Commercial Operations |
2012 |