Timeline
Here is the current projected timeline for the project:

Project Announcement May 2006
Air Permit Filing with Louisiana Dept. of Environmental Quality (LDEQ) February 2007
Regulatory Filings LA, AR, TX La. – Initially February 2007
Updated December 2007
Ark. – September 2006
Tex. -  August 2006
Major Procurement and Construction Contract July 2007
Public Utility Commission of Texas approval February 2008
Arkansas Public Service Commission Approval Pending
Louisiana Public Service Commission approval September 2008
Mobilize Site for Construction March 2008
LDEQ Permit March 2008
Gas Turbine First Fire February 2010
Commercial Operations June 2010