2021 Wind Energy Resource RFP

Southwestern Electric Power Company (SWEPCO), an American Electric Power company, has issued a 2021 Wind PSA RFP to obtain up to 3,000 megawatts (MW) of Wind Resources via multiple purchase and sale agreements (PSA) for purchase of 100% equity interest in the project companies selected.

Proposals will be evaluated based on criteria outlined in the final 2021 Wind PSA RFP. Projects must have a minimum name-plate rating of 100 MW and be operational by December 15, 2024, or December 31, 2025.

To qualify for consideration Wind Projects must interconnect to the Southwest Power Pool (SPP) RTO and be located in Arkansas, Louisiana, Texas, Oklahoma, Kansas or Missouri. Refer to the RFP for additional requirements (See Sections 4 and 9.1).

Proposals are due August 12, 2021. All proposal responses should be directed to the RFP Manager outlined in the RFP documents.

Schedule

Draft RFP Posted Online:  April 28, 2021
Bidders Technical Conference:  June 22, 2021
RFP Issue Date:  June 28, 2021
Notice of Intent:  July 16, 2021
Q&A Deadline:  August 6, 2021
Proposal Due Date:  August 12, 2021
Final Selection and Negotiation:  October 15, 2021
Execute Definitive Agreements:  March 11, 2022
File for Regulatory Approvals:  March 26, 2022
Required Regulatory Approvals:  No later than March 27, 2023
Notice to Proceed:  No later than April 28, 2023
Commercial Operation Date:  No later than December 15, 2024 or December 15, 2025

Bidders Technical Conference

Bidder’s Technical Conference was held on June 22, 2021. The Bidder’s Technical Conference presentation can be found in the Documents section above.
Place: Webex Event. Please email swepco2021rfp@aep.com for details.
Agenda: June 22, 2021 - Technical Conference Agenda.

Q&A

Questions should be directed via email to: SWEPCO2021RFP@aep.com.